PC CORRUGATED SHEET PILE WORK

SCOPE OF WORK

The Contractor shall design, furnish and install prestressed concrete corrugated sheet piles for intake and discharge channel work as indicated in Book II, "Summary Scope of Work ", in the Technical Specification refers to “General Civil and Architectural Design Requirements" and as shown on the drawings.

The work shall include furnishing all labor, material and equipment necessary to fabricate, deliver, install and test all sheet piles, complete.

CODES AND STANDARDS

Contractor shall comply with the requirements of Book II, "Codes and Standards".

The following codes and standards extracted from Book II, "Codes and Standards" are specifically applicable to the design, manufacture and testing of the work included in the Specification:

JIS                ..................... Japan Industrial Standard
ASTM           ..................... American Society for Testing and Materials
ACI                           American Concrete Institute


DESIGN REQUIREMENTS

 GENERAL

The bid of the offer drawing provided shows the conceptual design of sheet pile and minimum size of the length required as the result of preliminary design performed by the Owner.

The Contractor shall be fully responsible to provide sufficient size and length of prestressed concrete corrugated sheet pile to withstand the loads such as soil pressure, static and dynamic force of the ocean wave and others imposed on this structure. However, the requirement specified in sub clause refers to ‘LOADS’ below as a minimum shall be fulfilled by the Contractor.

LOADS

The following loads shall be considered in the design:       

Static water pressure        :    as per calculation

Seismic         :                       as specified in Book II

Soil pressure  :                       based on the specified sea bed level and dredging line as shown on the bid of the offer drawing.

Safety factors and load combination used in the design shall be in accordance with the requirements in Technical Specification.


SHEET PILE HANDLING AND TRANSPORT

Length of sheet piles shall be determined as to allow proper handling and transportation of sheet piles, and shall be subject to Owner's approval.

Completed sheet piles shall be transported and delivered to the site free of any damage.


LAY OUT

Contractor shall lay out and be fully responsible for correctness of such lines and grades and for proper execution of the work.

All surveying shall be in accordance with Specification refers to "Surveying and Setting Out" and "Erection and Commissioning"


PILING EQUIPMENT, INSTALLATION AND WORKMANSHIP

The Contractor shall submit with the bid proposal full details of the proposed pile driving equipment and the method of carrying out the work.

At all stages during driving, the pile shall be supported and restrained by means of leaders, trest, temporary supports or other guide arrangements to maintain position and alignment and to prevent buckling.

The piling equipment and driving force used shall ensure that the piles are installed without damage or loss of strength. If at any time in the opinion of Owner satisfactory results cannot be obtained with the equipment furnished by the Contractor, equipment of other rated capacity capable of driving piles to approved elevation shall be furnished and used by Contractor at no additional cost to the Owner.

MARKING AND LENGTH OF PILES

Marking of Piles

Each pile shall be clearly identified by its number in white paint at least every three meters, with a minimum of three locations at the top, bottom and middle. The Iength shall be marked and identified with white paint at least every meter. Intervals of 300 mm shall also be marked with paint.

Length of Piles

The length of the piles shall be as necessary to develop the required pile capacity.

SETTING OUT
The main setting out for the piles is to be completed prior to commencement of piling. Secondary or individual pile setting out is to be completed and agreed upon not less than 8 hours prior to commencing work on the piles concerned. All main setting out points, lines, stations, etc. are to be maintained safely and undisturbed.

DRIVING OF PILES

  Pitching and Driving

Piles shall be pitched accurately in the position and driven to the lines shown on the approved drawings.

Piles shall be driven using approved pile driving equipment. Where piles have to be driven below the level of the bottom of the leaders, extension leaders shall be fitted. The use of a follower or dolly will not be permitted except with the approval of the Owner.

The Contractor shall ensure that damage does not occur to the piles during driving. Protection of the entire length of pile shall be regulated to ensure that the piles are not overstressed during driving. Also, care shall be taken during driving to prevent and correct any tendency of piles to twist or rotate.

All piles shall satisfy the tolerances for position and inclination as stated herein. The deviation in position of the as‑driven centerline of a pile or the projection of its centerline from the pile center point as shown on the setting out drawings shall not exceed 75 mm when measured in a horizontal direction at the defined, level. Deviations from vertical shall not be more than 1 in 100.

If piles are installed out of plan position or line beyond allowable tolerances, the piles shall be extracted as requested by the Owner, to properly provide for load conditions and to avoid overstressing of piles. Manipulation of piles to force them into proper position or line will not be permitted. The Contractor shall be responsible to extract and/or drive additional piles as noted above at no cost to the Owner.

Any damaged pile shall be abandoned, replaced or repaired as approved by the Owner at the Contractor's expense. Additional piles shall be driven as requested, to provide for load conditions and to avoid overstressing of piles. The Contractor shall be responsible to drive additional piles at no cost to the Owner.

TEMPORARY PROTECTION OF PILES

The Contractor shall ensure that all freestanding piles are temporarily braced or stayed to prevent damage to the piles or loosening of the piles in the supporting ground. The attachment of temporary works, such as bracing or shuttering supports, to the permanent piles shall not be permitted.

EXTRACTION OF PILES

When extraction of the piles is required, it shall be carried out using efficient extraction equipment of adequate capacity. The extraction equipment shall be correctly positioned over the pile to minimize damage to the pile and to prevent any major disturbance of the supporting ground.

RECORDS OF PILE CONSTRUCTION

During the course of the work, the Contractor shall maintain a complete record of pile construction and the Contractor shall submit to the Owner, in an approved format, a record for each pile. Each pile record shall be submitted immediately after completion of each pile and shall include:

Type of pile

Pile number and all principal characteristics of the pile including dimensions.

Details of driving and installation sequence progress, including dates, times, equipment used and personnel (operator, engineer, etc.)

The equipment model number, weight and rated energy.

Actual location of piles as driven, with variations from plan locations indicated.

Variations in plumbness or batter.

Any unusual phenomena encountered in driving piles.

Depth and type of soil strata.

Artikel Terkait