ERECTION OF STRUCTURAL STEEL


SCOPE OF WORK
           
The scope of structural steel erection shall include the following as applicable to Contractor's work included in Book II refers to "Summary of Work" and in Book IIIA refers to "General Civil and Architectural Design Requirements'.

Unloading, storing, protecting, removing from storage and erecting the following:

Structural steel.

Gallery and auxiliary steel.

Performing all bolting work for field connections using high strength.
Furnishing welding electrodes and performing welding for field welded joints that are included in the Work.

Furnishing, and installing anchor bolts and anchor bolt sleeves into concrete foundations.

Laying out and verifying lines and grades as specified in here.

Grouting of column base plates.


CODES AND STANDARDS


The Contractor shall comply with the requirements of Book II refers to "Codes and Standards".

The codes and standards of the following organizations extracted from the Book II refers to "Codes and Standards" are specifically applicable to the design, manufacture and testing of the work included in this Specification:

AISC     ………… American Institute of Steel Construction
ASTM   ………… American Society for Testing and Materials
AWS     ………… American Welding Society


SUBMITTALS

ERECTION DRAWINGS

Erection and detail drawings for all parts of the work shall be prepared by the structural steel fabricator and coordinated with the erector to maximize shop fabrication and to minimize field fabrication as far as practical. These drawings shall also include erection and detail drawings for welding new steel to existing steel.

REPORTS

Copies of welding qualification reports, quality control reports, and other reports as specified or required, shall be furnished by Contractor to the Owner, during the course of the work, or upon completion of the work.

FIELD REPRESENTATIVE

The fabricator shall furnish a field representative to assistance in the coordination of the erection of the erection work at the site full time.

MATERIALS


WELDING ELECTRODES

Welding electrodes used for the Work shall conform to the applicable requirements of specification welding in steel structures.

EXPANSION ANCHORS

Expansion anchors shall conform to the requirements of Specification Concrete Expansion Anchor work and hall receive prior approval of the Owner.


PERFORMANCE

GENERAL PROVISIONS

Erection of structural steel shall conform to all requirements of the AISC Manual of Steel Construction (latest edition) and the following:

Lines and Grades

The Contractor shall lay out lines and grades from existing base lines and bench marks on the property, and shall be fully responsible for the correctness of these lines and grades and for proper execution of the work.

The Owner reserves the right to verify the correctness of these lines and grades during the progress of the work. This verification by the Owner will not relieve the Contractor of any responsibility for the work.

The Contractor shall preserve and maintain all benchmarks and reference points established. Should the Contractor during execution of the work destroy or remove any benchmarks and/or reference points established by the Owner, the cost for reestablishing these benchmarks and/or reference points will be charged to the Contractor.

Erection Tolerances

Steel work shall be set accurately to the established lines and grades and shall be plumbed and leveled such that the deviations in all completed work are within the tolerance limits and meet the requirements, as specified in the AISC Code of Standard Practice and this specification.

Column base plates shall be set at the specified elevations within the tolerance of ± 1.5 mm and shall be leveled within the same tolerance.

Fitting

Members and Details

Members and details shall be fitted into place by methods that will not injure the materials. Contractor shall replace any materials unduly injured, at Contractor's expense. Heating of anchor bolts in the field for bending or other purpose, and welding of ASTM A193 anchor bolts shall not be permitted.

Column Splices

In a column contact joint, the gap between column-milled surfaces not exceeding 0.8 mm will be accepted. If the gap exceeds 0.8 mm, but is less than 6 mm, it shall be packed out with no tapered steel shims. The shims shall be mild steel regardless of the column material. Gaps of 6 mm or more shall be reported to the Owner.

Misfits
Attention is specifically directed to the requirements of the. AISC Code of Standard Practice and Quality Criteria and Inspection Standards, that correction of minor misfits and a reasonable amount of cutting and reaming are considered a part of erection.

However, any errors in shop work which prevent proper field assembly and fit up of parts shall be reported, as soon as they are discovered, to the Owner as well as to the structural steel fabricator, so that the fabricator may either correct the errors or make substitution to be used.

The allowable limits for reaming the connection bolt holes for fitting in the field shall conform to the requirements of the AISC Quality Criteria and Inspection Standards. If fitting of bolts during erection in the field cannot be                                     obtained by reaming the fabricated boltholes within these limits, it is            considered that there are errors in fabrication, and these errors shall be rectified as mentioned before.

Correction of misaligned boltholes by the use of flame cutting is not permitted.

Field Connections
Connections of new steel to existing steel shall be made by welding, unless otherwise specified.

All other connections shall be made by high strength bolting, unless otherwise specified.

Where new steel is to be connected to existing steel, Contractor shall verify the locations, dimensions etc. of existing steel for alignment, prior to start of erection.

WELDING

All welding including stud welding shall be performed in accordance with the Specification Welding in Steel structures.

HIGH STRENGTH BOLTING

Type of Connection

FRICTION TYPE Connection, as specified in the AISC Manual and the "Specification for Structural Joints Using ASTM A325 Bolts" shall be used for all bolted connections unless otherwise indicated.

Types of Bolts

The following types of high strength bolts shall be used unless otherwise indicated.

 ASTM A325 Type 1 for all bolt sizes.

Assembly of Joints

Method of Installation

The Turn‑of‑Nut Tightening or Calibrated Wrench Tightening method, as specified in the AISC "Specification for Structural Joints Using ASTM A325 Bolts," shall be used.

Bolt and Nut Assembly

All nuts shall be fully engaged with a minimum of 6 mm projection of the installed bolt beyond the nut. The threaded part of the installed bolt shall not be in the shear plane. Reuse of bolts as specified in the AISC Specification for Structural Joints will not be permitted.

Fairing Up

The Contractor shall fair up the holes in each connection with enough pins to maintain the dimensions and plumb ness of the structure. These pins shall remain in place until all bolts in the balance of the holes have been tightened.

Washers

a.For an A325 bolt, a hardened flat washer shall be used under the bolt head or under the nut, whichever is to be turned in tightening.

b.Beveled washers shall be used as specified in the AISC Specification for Structural Joints Using A325 Bolts.

Location of Bolt Heads

a Columns: On outside faces of flanges.

b.  Beams and Girders: On upper sides of flanges.

INSTALLATION OF EXPANSION ANCHORS
Shall conform to the requirements of Specification Concrete Expansion Anchor work.

ERECTION DETAILS

Column Stiffener Plates

Column stiffener plates at connection joints with beams and girders may be shipped loose by fabricator and shall be installed by the Contractor.

Curb Angles and Guard Plates

All curb angles and guard plates are connected to structural steel in the shop.

For adjoining guard plates in continuous runs or at corners, the Contractor shall tack weld the ends together at the top.

Trolley Beams

The Contractor shall carefully align the bottom flanges of trolley beams at splices so that the upper surface of bottom flanges provides a smooth passage for travel of the trolley passing each splice.

Girt System

The girt system shall include horizontal girt, door, window and louver framing, and other vertical members attached to girt, parapet framing, sag rods, etc.

 The girt system shall be erected within the tolerances specified as mentioned before.

Sequence of Erection

Girt shall be erected in vertical sequence with the erection of structural steel to provide wall bays with girt completed from ground to roof. This will permit erection of siding in these bays without girt erection being carried on above siding erection at the same time.

Erection Around Door, Window and Louver Openings

Girt around such openings shall be erected in accordance with the following requirements:

a.All corners of openings formed by the junctions of horizontal girt and vertical members of the girt system shall be absolutely square.

b.Vertical and horizontal dimensions of openings shall each be within an overall tolerance of ± 1.50 mm for doors, ± 6 mm for windows, and + 6 mm to 0 mm for louvers.

c.Junctions of horizontal girt and vertical members at the head and sill of door openings will be detailed with end clearances not exceeding 6 mm nor less than 3 mm, and will be arranged for field welding closure of these junctions by the Contractor.
Stainless Clad Steel

General Processes

The installation of stainless clad steel shall conform to applicable requirements of the manufacturer for installation, welding, handling, protecting, etc. of that steel. Prior to installation, Contractor shall also consult with the manufacturer to insure the best possible installation of the material for the intended service.

Welding

a.The Contractor shall use stainless steel electrodes only, as specified in Welding in Steel structures or as recommended by the stainless steel manufacture, for all welding on the stainless clad side of the material. He shall perform all welding operations so as to reduce to a minimum, or completely eliminate, any weld spatter on the stainle3s clad side. Antis patter compound shall be used along both edges of welded joints, on the stainless clad side, to permit easier removal of any spatter that does occur.

b.Welds on the stainless clad side shall be reasonably smooth and shall blend smoothly into the adjacent metal; slight undulations in the length of welds will be acceptable, but all pits, crevices and other sharp discontinuities shall be corrected by the use of additional weld metal (if required) and by grinding to provide satisfactory welds.


Special Precautions

a.Do not attach any temporary materials, such as handles of lifting lugs, etc., to the stainless clad side of the material.

b.Any scratches, gouges, or damages to stainless clad surfaces shall be satisfactorily repaired by the Contractor at his own expense. Fill gouges and deep scratches with weld metal as specified for welding of stainless clad steel and grind and hand buff smooth.

Carefully remove weld spatter or other deposits on the surfaces flush with the surfaces and hand buff these areas smooth. Also remove discolorations, etc., using cleaning solutions and methods recommended by the manufacturer of the stainless clad steel.

c.All precautions shall be taken to provide ductile austenitic weld.

Temporary Shoring and Bracing

The Contractor shall be responsible for determining what temporary shoring and bracing must be provided to support loads to which the work may be subjected, including construction equipment arid the operation of such equipment. The Contractor shall be responsible for the adequacy and safety of such shoring and bracing.

FIELD CLEANING AND PAINTING

After erection is completed, Contractor shall clean and field touch up and field finish paint all structural steel, gallery steel and surge bins etc. in accordance with the requirements of Field finish painting unless otherwise indicated.


INSPECTIONS AND EXAMINATION


GENERAL PROVISIONS

This work is subject to inspection and examination by an independent testing laboratory at the project site, for full compliance with all requirements of this specification, the contract and Contractor's design drawings.

The Contractor shall retain and pay for the services of a testing laboratory, personnel or inspector(s) to perform this inspection and examination work.

The Contractor shall provide, and pay for all rigging required for the work and   for all personnel required to assist the inspector(s).

The Contractor shall furnish and install the tension-calibrating device. The device furnished shall bear a certification as to the accuracy of the device. Such   certification shall be dated not more than 30 days prior to the first actual use of the device for inspection of the work.

INSPECTIONS AND EXAMINATION OF WELDING

Shall be as specified in Specification Welding in Steel structures.

INSPECTION OF HIGH STRENGTH BOLTING

                        This inspection shall be performed in accordance, with the requirements of            Section 5 of the AISC Specification for Structural Joints using ASTM A325 Bolts, and will include the arbitration inspection specified therein.

In each connection on the structure, approximately 10% of the bolts will be inspected, but never less than two bolts.

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC)

Quality control shall conform to the requirements of Book II.

The quality control procedures shall include but not be limited to the following:

‑   Material certificates
‑   Welding
‑   Non destructive testing
‑   Cleaning and painting

The quality control documentation shall include but not be limited to the following:

‑ Material certificates
‑ Welding
‑ Field test and inspection reports.