EARTH EXCAVATION

SCOPE OF WORK
The Contractor shall perform excavation in accordance with this Specification and as shown on the approved drawings or as directed by the Owner.

Excavation shall include incidental clearing, grading, compacting, leveling, excavation and disposal of excavated materials, protection, sheeting, shoring, bracing and cofferdams, dewatering of excavation and work areas and preparation of bearing areas as required to properly install and complete the work, regardless of portion of the work for which dewatering is required and regardless of the nature of materials encountered in excavation, including construction of temporary diversion ditches, culverts, temporary access road etc. where required.


GENERAL EXECUTION OF EXCAVATION

The Contractor shall notify the Owner in writing at least three working days prior to the start of any excavation, the beginning of the work in any working area, to enable the Owner to verify all necessary levels and cross-sections of the original ground surface.  The Contractor shall, prior to starting excavation in any area, submit to the Owner a plan of operation with complete details of the method of excavation, type of equipment to be used, proposed method of diversion of drainage, safety measures to be used, etc.

The Contractor shall set out Works as shown on the 'approved drawings, utilizing the established benchmarks and coordinates.

The Contractor is responsible for the correct setting- out of Work.  Any additional work caused by his negligence in setting-out will be at his expense and corrective action must be carried out without delay as directed by the Owner.

The Contractor is responsible for all necessary safety measures from the commencement of work until it is completed.  The Contractor shall strictly follow safety regulations in order to prevent accidents.

The Contractor must take every precaution and use the most appropriate methods of excavation and equipment to avoid the loosening of material or the breaking of rock beyond the lines and grades shown on the drawings or as directed by the Owner. If for any reason whatsoever excavation is carried out beyond the lines and grades shown in the approved drawings, the Contractor shall, at his own expense, restore the required lines and grades with mass concrete.

Bottoms of all excavations must be trimmed to line and grade, the final 20 cm of excavation in any loose geological formation where concrete is to be placed shall be excavated by hand tools to avoid disturbance of the bottom, which will then be well rammed, all immediately prior to the placing of concrete.

Particular care shall be exercised when excavating in the vicinity of existing and partially or fully completed structures. The Contractor shall repair or replace, at his own expense, any structures or equipment damaged by his actions.

It will be the Contractor's responsibility to utilize to the fullest extent all materials from excavations which are approved and deemed suitable by the Owner as backfill or other construction.  The Contractor shall make his best efforts to comply with the above requirements.

Where possible, suitable materials shall be excavated separately from materials to be wasted and shall be placed in the designated final locations directly from the excavation or shall be stockpiled, if the immediate placement in the designated location is not possible.

PROTECTION AND SUPPORT

The Contractor shall provide protection and support required to properly installing work, for protection and support of adjacent structures and improvements as required for the safety of traffic and life.

Protection and support includes temporary sheeting, bracing and shoring and where indicated, permanent sheeting, bracing and shoring. Temporary sheeting, bracing and shoring shall be removed by the Contractor when their use is no longer required, unless otherwise directed by the Owner.

Excavation slopes shall be protected and supported, where required or when directed by the Owner, so that the slopes and bottom will be maintained for depth, width and condition indicated and so that adjacent structures or other construction will be protected from damage caused by any earth movement.

Protection and support shall be arranged for minimum interference with pipe laying, electrical installation and other similar work.

             
DEWATERING AND DIVERSION OF WATER

General
The Contractor shall furnish install and operate necessary incidental dewatering equipment as required to do all excavation in the dry.

Except where specifically permitted by the Owner, no surface run-off shall be pounded or restricted to a greater degree than would have occurred naturally either before the beginning of construction or after completion of the Work.

Diversion of Surface run-off

During the excavation and backfill work, the Contractor shall construct temporary drainage ditches, culverts and other structures as required and as directed by the Owner to divert/drain the work areas.

The Contractor's plan for diversion of the surface run-off are subject to review by the Owner. Before commencement of the Work, the Contractor shall submit to the Owner for review, drawings and data indicating his proposed plans for diversion and care of surface run-off.

The Contractor shall not place any fill across routes of natural drainage channels until the Contractor has made provisions to drain the surface run-off into a new diversion ditch.

No surface run-off shall be pounded or restricted to a greater degree than would have occurred naturally either before the beginning of construction or after construction of the work, unless approved by the Owner.  Any damage to any property, equipment or materials as the result of noncompliance to the above shall be the sole responsibility of the Contractor.

Dewatering
The excavation shall require installation of a dewatering system consisting of cofferdam/ cut-off walls, sumps and pumps of adequate capacities and other associated works.  The Contractor shall design, furnish and install a complete dewatering system and maintain the dewatering system in operating condition until the completion of his work.

The Contractor shall submit a design for the dewatering system proposed to be installed by him prior to carrying out the work.

The Contractor shall be responsible for the safety and functioning of the dewatering system installed by him.
The pumps, piping and the sumps installed shall have adequate capacity to keep the excavation dry for the entire construction period.

If any failure of the dewatering system occurs, the Contractor shall be responsible for correction of all deficiencies, and repair of any damages at no additional cost to the Owner.

The Contractor shall make available a standby electric supply system, or spare diesel pumps and spare parts for quick replacement for the continuous service of his dewatering system.

DISPOSAL OF EXCAVATED MATERIALS

Excavated materials which are not suitable as fill materials shall be hauled and disposed of in the designated spoil area.  The materials which are in excess of the fill requirements for the Contractor's work shall be hauled to the designated stockpile area.

The spoil area and the stockpile area shall be leveled, trimmed and graded to drain as directed by the Owner.

LINES AND GRADES

Excavation shall be perform to the lines and grades shown on the approved drawings or to the depth where suitable foundation conditions are encountered.

The Contractor must take all necessary precautions and utilize such methods of excavation that will prevent the disturbance of material and its possible displacement beyond the required excavation lines indicated on the approved drawings or as directed by the Owner.

Any over excavation, no compensation will be allowed and an approved material for back filling at his own expense.

EARTH EXCAVATION

Earth excavation means general excavation, including excavation from stockpile areas, of material such as clay, silt, sand, gravel, crushed or screened rocks, boulders of up to a volume of 0.75 m3, cemented or weathered rock which may be removed by hand tools, power shovels, dozers or other earth moving equipment and by ripping without continuous systematic drilling and blasting. Rippable material shall be defined as such that the materials can be removed by a properly equipped D8 Caterpillar, or similar, without excessive wear on the equipment.

Earth excavation may be accomplished by any method and by the use of any excavation and hauling equipment suitable for the work. Rock or boulders encountered in the excavation may be drilled and blasted whenever other methods of loosening such as ripping, crowbarring, or wedging prove impracticable and shall be removed as required.

In case that earth excavation shall not be carried out to rock or to specified levels as indicated on the drawings and the natural foundation material is disturbed or loosened, for any reason, the foundation shall be improved by compaction, or replaced with approved fill and compacted, or by other means as directed by the Owner.

TRENCH EXCAVATION

Trenches shall be excavated in hard and soft material to the limit lines and grades shown on the approved drawings or as directed by the Owner.

The Contractor shall furnish all labor, material and equipment required for the proper execution of the work.  Correct and adequate bracing and supporting of the excavation shall also be included.

Excavation performed beyond the lines and grades shown on the approved drawings, without specific instructions from the Owner, shall be back filled to grade and lines with approved materials. All additional work of this nature shall be carried out at the Contractor's expense.

Trenches for pipelines, steel pipes, ducts and conduits shall be excavated in straight sections and provide a minimum of 20 cm between the outside face of the pipelines, electrical duct or conduit and the side of the trench.

Mechanical excavation shall stop not less than 5 cm above the final bottom level and also at an approved distance from permanent works so that no damage occurs to the same.

The work shall include the excavation of the remainder, which shall be done and graded manually to provide uniform bearing on compacted soil immediately before the installation or placing of any equipment.

If the character of the material at any location in the bottom of a pipe trench is such that it might cause unequal settlement or provide unequal bearing for the pipe, or is otherwise unsuitable for the pipe’s foundation, unsatisfactory materials shall be removed and back-filled with granular materials and/or concrete and compacted as directed by the Owner at no extra cost to the Owner.

EXCAVATION FOR THE CONTRACTOR’S CONVENIENCE

This classification shall consist of -all excavation performed by the Contractor for the purpose of executing the Work, but not specifically shown, required or mentioned in the Contract Documents, such as excavation for haul roads, camps, shops, sanitary land fills and other similar excavation.  Permission shall be obtained from the Owner for the location of borrows areas and eventual spoil areas for unsuitable material.

The Contractor shall stabilize the slopes of such excavation in such a manner that they do not represent any danger to the public or property. Such excavation shall be performed at the Contractor's own cost and no separate payment will be made for this work.

PREPARATION OF BEARING AREAS

Bearing areas for foundations shall be inspected and approved by the Owner before any concrete is placed thereon.  If bearing areas are not suitable, as determined by the Owner, The Contractor may be requested to carry on the excavation deeper to more suitable bearing material.  Such additional excavation will be paid for on the Unit Price basis set forth in the Contract.  The Contractor may be requested by the Owner to make auger borings or other tests in bearing areas to determine thickness of bearing stratum.

Foundations shall be placed on undisturbed soil unless otherwise indicated.

Before placing any concrete on soil, the bearing soil shall be compacted as specified herein for type of fill material involved.  Surfaces shall be relatively smooth.

Before placing any concrete on soil that will absorb water, the surface of the soil shall be thoroughly wetted with clean water immediately before concrete is placed.

Artikel Terkait