PRE-COMMISSIONING

1.  GENERAL

This specification defines the minimum technical and operational requirements governing pipeline dewatering, drying and nitrogen packing of the Export Pipeline System. This specification is to be used in conjunction with the following documents:
         Basis of Design 84506-60-00-2L-060
         General Specification 84506-60-00-2L-000 - Definitions and Specification Directory
         General Specification 84506-60-00-2L-010 - Quality Assurance / Quality Control
         General Specification 84506-60-00-2L-020 – General Offshore Specification
         Cleaning Gauging and Hydrotesting Specification (845-60-30-2L-390)


2.  PROCEDURES – EXPORT PIPELINE SYSTEM

2.1       CONTRACTOR shall supply all equipment, materials and manpower to successfully complete all de-watering and drying operations and nitrogen packing of the pipeline to the satisfaction of COMPANY.
2.2       CONTRACTOR shall develop detailed pipeline pre-commissioning procedures for the pipeline and submit for COMPANY approval 30 days prior to the commencement of pre-commissioning activities. These procedures shall include as a minimum the proposed equipment and operations for the following:
         Dewatering pig train designed arrangement
         Disposal plan for fill water and chemical additive certificates
         Vacuum Drying
         Introduction of inert gas
2.3         Instrument stand(s) shall be manned at all times during pre-commissioning operations.  CONTRACTOR shall furnish communication equipment for use by CONTRACTOR and COMPANY during pipeline pre-commissioning, where CONTRACTOR employs personnel at different locations.
2.4       CONTRACTOR shall meet the following pre-commissioning requirements for a dew point –10 OC & nitrogen pack at +5 psi, although detailed acceptance criteria for each pipeline, or pipeline section shall be agreed between COMPANY and CONTRACTOR prior to start of pre-commissioning operations.

 

3.  PIG DESIGN

3.1       The design of pipeline pigs for bulk dewatering and drying the pipelines shall be the responsibility of the CONTRACTOR.  CONTRACTOR shall demonstrate to the satisfaction of COMPANY the suitability of any pig design.
3.2       The design of pipeline pig trains for bulk de-watering and drying the pipelines shall be the responsibility of the CONTRACTOR.  CONTRACTOR shall demonstrate to the satisfaction of COMPANY the suitability of any pig train design.
3.3       Pigs used during pre-commissioning may be launched from and received in temporary traps furnished and installed by CONTRACTOR for pipeline cleaning, gauging and hydrotesting.
3.4       COMPANY acceptance of any design or procedure will not absolve CONTRACTOR of his responsibility to complete the work in as diligent and as timely a manner as is practically possible.
3.5       Every pig shall be permanently marked with a unique number that shall be clearly visible in a photograph.  The condition of all pigs shall be recorded photographically prior to and following the pigging operation.
3.6         If in COMPANY opinion de-watering pigs have not adequately de-watered the pipeline, the dewatering operation shall be repeated until results obtained are satisfactory to COMPANY.
3.7         Refer Cleaning Gauging and Hydrotesting Specification (845-60-30-2L-390) page 8 paragraphs 4.7 & 4.8.

 

4.  DEWATERING REQUIREMENTS

4.1       A flow meter of sufficient size and accuracy shall be used to measure the quantity of drying gel, water absorbent liquid, air or inert gas required to bulk dewater and dry each pipeline, or pipeline section.  CONTRACTOR detailed pre-commissioning procedures shall include methods and equipment used to measure and monitor pumping rates.
4.2       During bulk de-watering of the pipeline, samples of water shall be taken from between each pig batch for salt testing.  Acceptance of the first bulk de-watering operation shall be based on the test results of the last fresh water batch.  The salt content in the last batch shall be less than 200 ppm.  Should the salt content exceed 200 ppm, CONTRACTOR shall re-swab the pipeline with additional fresh water batches.
4.3       CONTRACTOR shall be responsible for proper dilution and remediation or disposal of any chemical additives used during the pipeline hydrotest, subject to prior approval by both COMPANY and AUTHORITIES.

 

5.  DEWATERING PIG VELOCITY AND DRIVING PRESSURE

5.1       Dewatering pigs shall be driven at a speed of between 0.3 meters/second and 0.7 m/sec for the initial bulk de-watering run, and a speed of between 0.5 meters/second and 0.7 m/sec for additional runs if required. 
5.2       Driving pressure shall be recorded on a COMPANY-approved recording pressure chart.  Chart time shall correspond to actual time.  Charts and other data relating to dewatering operations shall be submitted to COMPANY at the completion of each run.
5.3       Pumps shall be capable of driving pigs at the required speed and pressure range.  Pressure, volume and temperature shall be monitored and recorded at all times during the pigging operations.
5.4         Should any pig become stuck, operations shall be shut down, the pig located and cut out of the pipeline and the pipeline shall be repaired.  Repaired pipeline sections shall then be cleaned, regauged, re-hydrotested and dewatered.
5.5         Refer Cleaning Gauging and Hydrotesting Specification (845-60-30-2L-390) page 5 section 3 Pig Design.

 

6.  VACUUM DRYING EQUIPMENT AND INSTRUMENTS

6.1       Dew point, vacuum and temperature recorders, equipped with 24 hour recording charts, shall be used to record time, dew point, vacuum and ambient temperature during vacuum drying operations.  Vacuum recorders shall have an accuracy and repeatability of zero point one percent (+/- 0.1%).  Dew point and temperature recorders shall be accurate to 0.1oC.  Temperature effects on the dew point shall be evaluated by a qualified person, and shall be taken into account in determining the correct dew point.
6.2       Vacuum drying shall be performed in accordance with COMPANY approved procedures and schedules that shall reflect the required completion of individual pipeline sections.
6.3       Vacuum-recording instruments shall be tested and calibrated before pre-commissioning begins.  Vacuum recorders shall be capable of measuring in increments of 10.0 kPa.
6.4       Dew point and vacuum recorders and gauges shall be installed in parallel on a manifold, with individual instrument valves and vents.  CONTRACTOR shall provide to COMPANY calibration certificates from an independent laboratory for the chart recorders and gauges, showing they have been calibrated within sixty (60) days prior to use.
6.5       Vacuum pumps shall be connected to the system through a check valve and leakproof block valve.  Vacuum pumps shall be easily separable from the system to be evacuated.

 

7.  VACUUM DRYING

Vacuum pumps shall be equipped with a digital counter, that shall be zeroed before starting.  During evacuation operations the counter reading and vacuum gauge reading shall be recorded, with time of day, at 15 minute intervals.  Mean pipeline temperature shall be recorded at the beginning and end of commissioning and at least two (2) hour intervals.  Completed vacuum drying charts shall be submitted to COMPANY on completion of pipeline commissioning.

7.1 Vacuum Drying
Vacuum drying of the pipelines shall require the effective removal of the residual water to achieve an absolute level of moisture as detailed in Section 2.4. Vacuum drying operations shall commence upon completion of dewatering and vacuum shall be pulled from at least two points in the pipeline system.
CONTRACTOR shall monitor the pipeline temperature during drying adjacent to the vacuum plant to ensure that freezing does not occur due to excessive vacuum drawdown.  In the event of freezing, the vacuum units shall be taken off-line until the freezing has stopped.  Hand held radiation thermometers should be used to determine pipeline temperature.
The vacuum drying operation shall comprise the following steps:
CONTRACTOR shall run the vacuum plant on the temporary pipework down to a pressure of 1 mbara to ensure it is leak tight.  When the temporary pipework is leak tight the Gas Export Line shall be depressurized to 200 mbara, recorded at the pipeline ends, and held until all major leaks have been repaired and the CONTRACTOR is satisfied that any remaining leakage shall not affect the achievement of the acceptance criteria.
The leakage rate shall be quantified for a specific pressure.  The leakage rate shall not exceed 10% of the vacuum spread capacity at 1 mbara.
The pressure in the pipeline shall be gradually reduced.
During this phase the pressure shall be gradually reduced to a pressure lower than the saturated vapor pressure.  The vacuum shall be maintained until the Contractor and Operator are satisfied that this phase is complete and that a pressure reading of 1 mbara or less is consistently recorded.
The low-pressure air purge shall be carried out by allowing dry airflow into the pipeline whilst simultaneously pulling vacuum at the opposite end.  The pressure shall be allowed to rise above the saturation vapor pressure to a more efficient pumping pressure (approximately 20 mbara).  The purge air at the purging pressure shall have an absolute level of moisture which is lower than a vapor content of 0.8835 gm/m3.  The purging shall continue until at least two pipeline volumes at the purging pressure, have been passed through.
This phase shall be considered complete when consistent internal dewpoint readings of ‑10oC or lower are achieved over a period of time.
The pressure shall be drawn down to 1 mbara or less.  The Contractor shall then isolate the pipeline system and perform a soak test, holding the pressure for 24 hours.
This phase shall be considered complete when either the pressure remains at 1 mbara or the increase in pressure is demonstrated to be caused by temperature variation or leakage quantified but not rectified during the leak test.  Evidence that the pressure time plot, for reducing pressure from the air purge pressure of 15 mbara down to 1 mbara, is significantly different from the original pressure time plot may also be used to gain acceptance of the soak test.
The air in the pipelines shall be replaced with nitrogen (purity greater than 99% nitrogen) to the positive pressure given in Section 2.4.
Nitrogen shall be introduced at one end of the pipeline, with a dew point lower than ‑50oC, at a controlled rate to prevent over compression and subsequent re-condensation of water.  The rate and controlling pressure shall be determined and approved by COMPANY prior to introduction of nitrogen.  As the pressure increases in the pipelines the nitrogen pack rate may increase.
The nitrogen dew point at the outlet end of the pipeline shall be monitored.  This phase shall be considered complete when the nitrogen dew point is lower than    -10oC at atmospheric pressure and pipeline packed to final pressure.
7.3 Demobilization
Once the dewatering operation has been accepted, Contractor shall remove temporary pig launchers and receivers as appropriate.
The Contractor shall ensure that all consumables, temporary equipment and personnel are removed from site in a timely manner.  The Contractor shall leave the site in a condition as good or better than it was before mobilization

8.  ACCEPTANCE CRITERIA

The dewatering phase shall be accepted on the following basis:
         All the dewatering pigs have traversed the pipeline and that the last three pig’s sealing disc diameters remain greater than the nominal pipe bore.
         Relatively small volumes of water precede the last two pigs.
         Water preceding the final pig has a salt content less than 200 ppm.

The vacuum drying shall be accepted on the following basis:
         Pressure of 1 mbara is achieved
         Air purge achieves a dewpoint of less than -10oC
         Drawdown following air purging indicates the line is dry
         Soak test indicates minimal pressure rise
         Nitrogen pack dewpoint indicates the line has achieved specification

 

9.  SUBMISSIONS BY THE CONTRACTOR

In addition to the requirements stated herein, CONTRACTOR shall combine and submit to COMPANY all documents, records, charts and test certificates in a detailed final report at the end of the job.
All data to be submitted to COMPANY in both hard copy and electronic format.

Artikel Terkait