8.1 GENERAL
To supervise the contractor's project execution activities, PLN signed a contract with the Consultant associated with a local Consultant to obtain services, which includes the construction supervision service. 8.2 SITE INSTRUCTION
To supervise the contractor's project execution activities, PLN signed a contract with the Consultant associated with a local Consultant to obtain services, which includes the construction supervision service. 8.2 SITE INSTRUCTION
The consultant shall actively assist PLN with construction supervision activities including but not limited to : (a) Review and comment on the contractor's execution of site works.
(b) Review, comment on and monitor the contractor's project construction schedule.
(c) Assist in inputting and updating PLN's Artemis construction schedule.
(d) Review and comment on contractor's activity progress report (weekly, monthly and quarterly progress report).
(e) Review and comment on contractor's construction quality assurance program, practices, test and results for any equipment and system specified in the contract.
(f) Review and comment on contractor's construction practices to minimize deleterious effects on environment and ecology, with due consideration given noise level and safety.
8.3 INSPECTION OF WORK
The inspection of work should be conducted by joint PLN Site Project/Consultant's Supervision and other relevant discipline engineer in order to obtain factual data which is necessary for supporting relevant data in acceptance and certification of the complete work of system or subsystem of the project.
8.4 CONSTRUCTION SURVEILLANCE
The project construction work performance of the contractor will be continuously and closely monitored by joint PLN Site Project/ Consultant's Supervision according to the specification codes (including the safety code and environmental maintenance), standards and contract.
8.5 DOCUMENTATION
In order to establish a degree of control and formality in dealing with Construction related activities the following documentation procedures have been provided:
a) Inspection Application and Inspection Report.
b) Construction Defect Reports.
Samples of Report, Notes of Guidance on use, document flow charts and Registers are contained in Appendix 8.1
c) Site Change Requests.
d) Site Instruction.
This Instruction is intended for limited use when other routine forms of Contractor instruction have met with negative response and a direct, written instruction is necessary: It carries no financial commitment but never the less is an authoritative document and must be used judiciously.
Samples of the Site Instruction together with a document flow chart and Register is contained in Appendix 8.3.
8.6 PROGRESS MONITORING
(a) Review and comment on contractor's progress reports (weekly, monthly and quarterly).
(b) Review and update the contractor's schedule.
8.7 PHOTOGRAPHS
Photograph will be taken to provide a clear picture of the construction progress for individual equipment, subsystem and system.