APPENDIX 1
A1.1 Facility Codes
A1.2 System Codes
A1.3 Discipline Codes
APPENDIX 2
A2.1 Document Types
APPENDIX 3
A3.1 Drawing Category (Type)
1.0 PURPOSE
The purpose of this procedure is to provide guidelines for:
•
The
correspondence coding system.
•
The
document numbering system.
•
The
drawing and specification numbering system
•
Logging,
distribution and filing of project related outgoing, incoming and internal
correspondence
•
Logging,
distribution, reviewing, issuance of comments, approval and filing of
Contractor prepared engineering documents
Note: E-Mails are not to be used for formal,
contractual matters between Company and Contractor. However if an important or
significant e-mail is produced or received during the course of the Project the
originator or primary recipient is responsible for printing a hard copy and
sending to file.
Upon
project completion, all relevant information must be compiled in Jakarta head
office to satisfy operational, legal and statutory requirements. Compliance
with these guidelines will allow this to be carried out in a timely and
efficient manner after the records have been transferred from the various site
locations to the Jakarta head office.
2.0 SCOPE
The
scope of this procedure extends to all correspondence and engineering documents
generated during the ADGF Project.
3.0 RESPONSIBILITIES
These
guidelines will be followed by all Company and Contractor project personnel at
all site locations so that records and information are indexed, stored,
distributed and made available to users in an efficient and cost effective
manner.
Note:
Contractor shall be responsible for the review, revision and re-issue of all
drawings re-numbered to meet the requirements detailed in Section 7 of this
procedure.
4.0 DEFINITIONS
AND ABBREVIATIONS
Not Applicable
5.0 CORRESPONDENCE CODING
5.1 Purpose
To
define the correspondence coding system to be used on all outgoing and incoming
correspondence generated and received during the ADGF Project, including
letters, faxes, memos and transmittals etc.
5.2 Procedures
The structure of the document coding
shall be as follows:
5.2.1 Outgoing
Correspondence: 84506-X-NNNN
¨
84506 is the ADGF Project Code assigned by the project group in
Houston
¨
“X” is the Document Type where :
¨
L
= Letter
¨
F
= Fax
¨
M
= Memo or Interoffice Communication
¨
T
= Transmittal
¨
D
= Document / Drawing Transmittal
¨
“NNNN”
is the Sequential Number for each item of outgoing correspondence
Note that blocks of numbers will be issued for correspondence
originating from each Project Office / Site Location as follows:
0001 – 0999 ADGF
Jakarta Office
1000 – 1999 Site
Office 1
2000 – 2999 Site
Office 2
In the event that an office location uses all the assigned numbers, the
next available ‘000 series will be assigned to that location.
Example - Correspondence Out - 84506-L-0066
84506 (Project ID) - L (Letter) – 0066
(Document number 66 in the unique sequence).
5.2.2 Incoming
Correspondence
Incoming correspondence will be logged
on receipt in the “ADGF Incoming Correspondence Log” and assigned a unique
number by the system.
After logging in the system, incoming
correspondence will be stamped with the following details:
¨
Distribution
(Addressee for action plus copies for information to appropriate Team members)
¨
Project
File Code Number (ADGF Project uses the 19.0 Series)
¨
The
unique number assigned by the Incoming Correspondence log system
The Document Controller will then
distribute the document copies as appropriate – originals to be filed in the
correct Project File.
5.3 Distribution Matrix
Distribution of correspondence shall be
by the approved distribution matrix. This matrix will assign the primary action
and distribution of incoming correspondence, reports and minutes of meetings.
Each ADGF Project office shall develop
their own distribution matrix in accordance with their particular requirements.
6.0 DOCUMENT NUMBERING
6.1 Objectives
To define the document numbering system
to be used on documents such as procedures, reports,
studies etc. produced for the ADGF Project. Note that Drawings and Specifications are numbered using the system
detailed in Section 7.0
6.2 Policies
All “internal” CIIL Project Control
Procedures will be numbered using an abbreviated system so that unnecessary
zeros are not incorporated in the document number e.g. IFR/PS/PR/84506-00-001
If a Procedure is issued to a
Contractor as part of the Bid documentation, then the Procedure will be
renumbered using the full ADGF document number, e.g. IFR/PS/PR/84506-0000-00-001.
This will ensure consistency with the numbering system used for Drawings and
Specifications that are also issued externally.
6.3 Procedure
All documents detailed in Section 2.4
will be numbered in accordance with the following system:
IFR – SS – TT - 84506 - BB - XXX
|
|
||||||
|
|
|
|
Sequential Number
|
|||
|
|
|
|||||
|
|
|
System Code ID Number
|
||||
|
|
||||||
|
|
Project ID Code (84506)
|
|||||
|
|||||||
|
|
Document Type
|
|||||
|
|||||||
|
|
Functional Area
|
|||||
|
|||||||
|
|
Infrastructure Ref. (IFR)
|
|||||
|
|||||||
IFR is
the Infrastructure Group Reference
SS is
the Functional Area Code e.g. “PE” – Project Execution
TT is
the Document Type e.g. “PR” - Procedure
84506 is the ADGF Project Code issued by
the Project Group in Houston
BB is the System Code e.g. 31 -
Manifolds. (Appendix A1.2)
NOTE: Internal CIIL Project Control Procedures are ALL numbered “00”
XXX is
the Sequence number of the Document, starting at 001
Electronic
document files shall be saved as the document number with a suffix denoting the
revision status (e.g. IFR/PS/PR/84506-00-001-A for revision A).
6.4 Functional Area Code
This identifies the Functional Area within Infrastructure group
who prepared the document, where:
MA - Management
DE - Development Engineering
PE - Project Execution
QA - Safety, Environment and QA
PS - Project Services
GR - Government Regulations
OP - Operations Planning
6.5 Type of Documents
Policy
(PO) This is a document that contains
instructions by the ADGF Project management that must be strictly followed
across the ADGF Project. Policies are
typically set at the management level.
Sub-Management
System (MS)
This
is a document that sets out, at a high level, the key processes, organization
and related documents for a specific part of the system.
Procedures (PR) Documents
that fully define the preferred manner, working methods and reporting criteria
to be used by the Project Team in performing significant Project activities.
Work
Instruction (WI) The
detail the basic activities for the
actual performance of the work and apply at the level where the physical work
is being performed.
Guidance
Note (GN) These
documents are generally issued to document certain good practices, obtains
consistency and generally informs individuals of efficient ways of working.
Reports (RE) Documents
used to document the results of certain engineering calculations, laboratory
tests, field studies, or analyses. They
can be documents generated by the project Team personnel or received from
outside parties. When a report is
received from an outside party it will be assigned a number and logged into the
Project Document Control System as if it had been generated internally.
Miscellaneous (MI) Documents which are produced on a less frequent basis
than those described above.
7.0 DRAWING AND SPECIFICATION NUMBERING
7.1 Objective
To define the numbering system to be used on
all Drawings and Specifications produced for the ADGF Field Development
Project.
7.2 DRAWING NUMBERING
All drawings shall
be numbered in accordance with the system described below:
84506 – BB - CC - DD – XXX
|
|
|||||
|
|
|
|
|
|
Sequence Number
|
|
|
|
|
|
||
|
|
|
|
|
Drawing Category
|
|
|
|
|
|
|||
|
|
|
|
System Code ID
|
||
|
|
|
||||
|
|
|
Facility Code
|
|||
|
|
|||||
|
|
Project ID Code
|
||||
|
||||||
Where:
84506 is
the CII ADGF Project Code
BB is
the Facility Code ID e.g. 60 – Infield Flowlines. (Appendix A1.1)
CC is
the System Code e.g. 31 - Manifolds. (Appendix A1.2)
DD is
the Drawing Category e.g. 24 Riser/Manifolds Gas
XXXX is
the Sequence number of the Drawing, starting at 001 and the unique attributes
based on the combination of BB, CC, and DD.
Electronic document files shall be saved as the document
number with a suffix denoting the revision status (e.g. 84506-6031-24-001-A for
revision A).
7.3 APPLICATION OF ADGF DRAWING NUMBERS
This section deals with the various
types of documents to which Drawing/Document numbers shall be assigned and the
manner in which they should be assigned.
The following identifies the minimum
key deliverables, which shall be awarded Drawing / Document numbers, but shall
not be limited to:
-
General
-
Overall
Plot Plan
-
Process
-
Process
Flow Diagram
-
P&ID’s
-
One
Line Diagrams
-
Utilities
-
Pipelines
and Subsea
-
Structural
-
Subsea
Equipment
-
Safety
Drawings
-
Pipeline
Schematics
-
Pipeline
Alignments
-
Pipeline
Risers
-
Pipeline
Appurtenances
-
Pipeline
to Piping Interfaces
-
Equipment
G.A.’s
-
Piping
G.A.’s
-
Isometrics, including pipe support details, P&ID number, system,
number and area
-
Installation
Details
-
Tie-In
Details
-
Spares
-
Structural
-
Layout
Drawings
-
GA
Plans and Sections
-
Structural
Steelwork
-
Structural
Details
-
Instrumentation
-
Instrumentation
Drawing Index
-
Control
Panels with Details
-
Instruments
Schematics and Loop Drawings
-
Installation
Details
-
Instrument
Index
-
Distributed
Control System (DCS)
-
Safety/Loss
Prevention
-
Area
Classification, including Schedule of Sources of Hazard
-
Diagrams
showing Cause and Effect Charts
-
Marine
Systems
-
Vessel
Arrangements
-
Tanks
& Vessels
-
Pig
launchers / Receivers
-
Pressure
Vessels
-
All
Supplier and Sub-Supplier Drawings
7.4
SPECIFICATION
NUMBERING
All Specifications
shall be numbered in conformance with the numbering system described below:
84506 – BB - CC - DE – XXX
|
|
|||||
|
|
|
|
|
|
Sequence Number
– 001, 002, 003, etc
|
|
|
|
|
|
||
|
|
|
|
|
Discipline Code
e.g. 2 = Pipelines,Flowlines, Umbilicals Document Type e.g. L = Specification
|
|
|
|
|
|
|||
|
|
|
|
System Code ID
e.g. 30 = Pipelines and Flowlines
|
||
|
|
|
||||
|
|
|
Facility Code
e.g. 60 = Infield Flowlines
|
|||
|
|
|||||
|
|
Project ID Code - 84506
|
||||
|
||||||
8.0 REVISION NUMBERING
During the Project Execution Phase
being carried out by Conoco, several distributions will take place for the
purpose of obtaining approvals necessary for the optimization of the design
facilities.
These preliminary documents, being the
stage prior to drawings issue for the EPCI bid process, shall be labeled with
the revision letters “A”, “B”, “C”, etc.
Changes made during this phase are not formally recorded. The revision detail shall be included in the
comment box as part of the drawing Title details.
Drawings for inclusion in the Bid
Documents will be numbered according to the procedure described in Section 3.2
– Drawing Numbering, with the addition of the correct Revision Number on issue
of the Bid documents.
Following award of the EPCI contract,
when mutual agreement between the Conoco ADGF Project Team and the EPCI
Contractor has been obtained, the drawings will be labeled with the Status Code
“AFD” “Approved for Design”. Any
revisions thereafter will be recorded next to the Title block as a permanent
record of change, and the changes will be flagged with a triangle with the
revision number. All drawings to be
issued following AFD shall be issued with the revision “A1” with subsequent
revisions labeled “A2”, “A3” or “B1”, “B2”, “B3” etc. depending on the revision
status.
When the design work is frozen, the drawings
shall be assigned the Status Code “AFC” - “Approved for Construction” and the
initial revision shall be “0” (zero) and subsequent revisions shall be
designated “1”, “2”, “3” etc.
At completion of the work all
applicable drawings will be assigned the Status Code “ASB” - “As Built” and the
revision raised to acknowledge completion.
Example: A - Pre Bid initial issue
B - After initial review/comments
C - Any further revisions
AA - Issued for Bid
BB - Subsequent revisions prior to contract award.
AFD- Authorized for Design
A1- Subsequent revisions prior to completion
of design work
AFC- Authorized for Construction
O - Initial AFC revision
1 - Subsequent revisions until as-built status.
00 General
10 Not
used
20 Not
used
30 Not
used
40 MOgPU
Topsides
50 Subsea
60 Infield
Flowlines
70 Export
Pipeline
80 Reservoir
The
following main system groups are used:
00 - 09 Other
Systems
10 - 19 Marine
Systems
20 - 29 Process
Systems
30 - 39 Drilling
and Well Related Systems
40 - 49 Process
Support Systems
50 - 59 Utility
Systems (Not Used)
60
- 69 Utility Systems (Not Used)
70 - 79 Safety
and Facility Systems
80 - 89 Electrical,
Communication and Instrumentation Systems
90 - 99 Structural
Systems and Cathodic Protection Systems
Other
Systems
00 General
Systems
01 Temporary
Systems
Marine
Systems
10 Ballast
System
11 Moorings/Anchors
and Anchor Patterns
Process
Systems
20 Not
Used
21 Not
Used
22 Process
Gas
23 Gas
Compression
24 Gas
Treatment
25 Gas
Export and Metering
26 Not
Used
Drilling,
Well, Pipelines and Subsea Related Systems
30 Pipelines
and Flowlines
31 Manifolds/PLEMs
32 Wellheads
33
Controls
34
Umbilical
34
Risers
35
Tees
36
Spools
Process
Support Systems
40 Not
used
41 Not used
42 Chemical
Injection
43 Flare,
Vent and Blowdown
44 Produced
Water Treatment
Utility
Systems
50 Not
used
Utility
Systems
60 Not
used
Safety
and Facility Systems
70 Not
Used
71 Not
Used
72 Not
Used
73 Not
Used
74 Not
Used
75 Not
Used
76 Not
Used
77 Not
Used
78 Not
Used
79
Emergency
Shutdown System
Electrical,
Communication and Instrumentation Systems
81 Main
Power HV/MV
82 Main
Power LV
83 Lighting
and Small Power
84 Essential
Power
85 Battery
Systems and UPS
86 Telecommunication
87 Instrument
Systems
88 Earthing
and Lightning Systems
89 Trace
Heating and Misc. Dist. Power
Structural
Systems and Cathodic Protection Systems
91 Not
Used
92 Structure,
Topside
95 Not Used
96 Structure,
Subsea Structure / Template
0 General
1 Mechanical
2 Pipelines,
Flowlines and Umbilicals
3 Electrical
4 Instrumentation
and Subsea Controls
5 Civil
6 Structural
and Offshore Buildings
7 Well
Systems
8 Marine
Systems
9
Tanks,
Vessels, Columns and Reactors
A - User Guides
B - Design Books
C - Operating Manuals
D - Manufacturing Data Books/Mechanical
Catalogues
E - Fabrication Dossiers
F - Systems Test Dossiers
G - Change Control Records
H - Engineering Standards
J - Calculations
K - Reports/Technical Notes/Special
Studies
L - Specifications
M - Equipment Datasheets
N - Coatings, Navigational, Marine
Machinery
P - Project Procedures
R - Project Controls
S - Inspection and Testing Requirements
T - Vendor Document Requirements
U - Engineering Registers
V - Bid Documents/Pre-Qualification
Documents
W - Procurement (P.O.’s, RFS’s etc)
General
Drawings
00 Drawing
Index General Drawings
01 P&ID
Legend Sheet
02 Instrument
Details
03 Process
Flow Diagrams
04 Safety
Drawings
05 P&ID
Diagrams - Process
06 P&ID
Diagrams - Utilities
07 Equipment
Arrangements
08 Piping
Studies, General Sketches, 3 Dimensional Drawings
09 Field
Layout Drawings
Mechanical
10 Drawing
Index Mechanical Drawing
11 Piping
Plans, Sections & Details
12 Pipe
Support Details
13 Not
Used
14 Not
Used
15 Not
Used
16 Piping
Isometrics
17 Piping
BOM
Pipelines
and Flowlines
20 Drawing
Index Pipelines and Flowlines
21 Pipeline
Layout Drawings
22 Pipeline
Schematics
23 Pipeline
Alignment, Profile and Approach Drawings
24 Riser
and Manifold General Arrangement Drawings
25 Riser
and Manifold Plans, Sections & Details
26
Miscellaneous
Pipeline Details
27
Installation
Details
Electrical
30 Electrical Drawing Index
31 Area
Classification Drawings
32 One
Line Diagrams
33 Interconnecting
Wiring Diagrams
34 Electrical
Cable Schedules
35 MCC
Schematics
36 Electrical
Equipment Plans
37 Miscellaneous
Electrical Details
38
Electrical
BOM
39
Open
Instrumentation
40 Instrumentation
Drawing Index
41 SAFE
Charts & Logic Diagrams
42 Control
Panels with Details
43 Instruments
Schematics and Loop Diagrams
44 Instrument
Wiring Diagrams
45 Installation
Details
46 Instrument
Schedule
47
Instrument
BOM
Civil
50 Civil
Drawing Index
51 Not
used
52 Geotechnicaland
Piling
Structural
and Offshore Buildings
60 Structural
Drawing Index
61 Primary
Structural Drawings
62 Secondary
Structural Drawings
63 Miscellaneous
Structural Details such as Pipe Supports, Monorails, Access Platforms, etc.
Well
Systems
70 Well
Systems Drawing Index
71 Subsea
Wells
72 Well Riser System
73 Tubing/Downhole
Equipment and Tools
74 Surface
Equipment
75 Subsea
Manifolds
76 Subsea
Trees
77 Subsea
Jumpers
78 Well
History Reports
79 Well
Stimulation and Perforation
Marine
Systems
80 Marine
Systems Drawing Index
81 Vessel
General Arrangement Drawings
82 Mooring
/ Anchoring Details