CONVEYING, PLACING AND CONSOLIDATING CONCRETE

CONVEYING
After being discharged from the mixer the concrete shall be transported as rapidly as possible, which in no case shall exceed 30 minutes, to its the final position in the Works, by means that shall be approved by the Owner and which shall prevent segregation, loss or contamination of the ingredients. The containers that convey the concrete shall at all times be kept clean and free from hardened or partially hardened concrete.
Chutes or other equipment for conveying concrete shall be of such size and design as to ensure a continuous flow of concrete at delivery and without separation of ingredients, and shall be thoroughly cleaned before each run. If use of pumping equivalent to convey concrete is selected, aluminum pipe shall not be used. Pipe or other equipment where aluminum surfaces will be in contact with plastic concrete shall not be used. A steel piping arrangement utilizing a "Y" will be permitted provided a valve is installed at the branch point to direct the flow into one branch at a time. Minimum pump line size of 150 mm shall be provided for 20 mm and 40 mm maximum size aggregate mixes. For mixes containing aggregate less than 20 mm maximum size, a smaller line may be used. 

Concrete shall not be allowed to drop freely more than 1.50 m. For drops which exceed 1.50 m use a hopper and drop chute.

PREPARATIONS FOR PLACING CONCRETE
Before concrete is placed, forms and reinforcing shall be cleaned of dirt, debris. All necessary trenching, damning, draining and pumping shall be done so that all concrete can be placed in the dry. Concrete shall not be placed until forms and reinforcing have been inspected and approved by Owner. 

For preparation of construction joints, the provision mentioned herein of this specification shall be strictly complied before fresh concrete is placed on or against hardened new concrete or old concrete, thoroughly clean surfaces of all laitance, soft or loose materials and deleterious substances. The surfaces shall then be washed clean and thoroughly moistened. 

Dry concrete surface shall be saturated for at least 24 hours. Immediately before fresh concrete is deposited, horizontal surfaces shall be covered with cement mortar of same mix as concrete to be poured. Fresh concrete shall then be placed before cement mortar has obtained its initial set.

All reinforcing and embedded steel shall be washed with clean fresh water using a high pressure jet to remove surface chloride contamination immediately prior to placement of the concrete.

Washing shall be repeated if the steel is subsequently immersed in or contaminated by sea water.

PLACING OF CONCRETE
The Owner shall be given 24 hours notice before any concrete is poured in order that he may inspect the work in writing.
Concrete shall not be placed until all forms, embedded items and the surfaces upon which the concrete is to be placed have been approved by the Owner. Concrete shall be delivered to the forms by methods ensuring its required consistency without excessive loss of slump or segregation. Concrete shall be deposited in all cases as nearly as practicable directly in the final position and shall not be caused to flow in a manner to permit or cause segregation. Concrete shall not be moved to its final location by the use of vibrator. 

All concrete shall be placed in a continuous pour over the area between construction joints in an uninterrupted operation in such manner as to form a monolithic structure, the component parts of which are securely bonded together. Do not deposit segregated concrete or concrete that has partially hardened or been contaminated by foreign materials, nor use retempered concrete. Time interval between placing of successive batches of concrete shall not be greater than 30 minutes. 

All concrete shall be deposited in forms within 1 hours after introduction of mixing water to cement and aggregates unless otherwise required. 

All concrete in vertical members, such as columns, and walls, shall be in place not less than 2 hours before any concrete is placed in girders, beams or slabs to be supported thereon. Concrete for beams, girders, brackets, column caps, and hounches shall be placed monolithic with floor slabs.

Concrete shall be deposited in horizontal layers no deeper than 60 cm.
Hot Weather Concreting
Hot weather concreting shall comply with ACI 305 and the following :
Suitable means shall be provided to ensure that the temperature of the concrete when it is placed in the work shall not exceed 32 0C.
Where necessary aggregate stockpiles shall be shielded from direct sunshine and/or sprayed with fresh water especially when evaporation rates are high. Due allowance shall be made for the extra water in the concrete mix design. Mixing water shall be kept cool with insulated pipes and open tanks, refrigerated or ice added as necessary, and cement shall be stored in light colored silos or sheds.Where necessary the surfaces, including reinforcement, against which concrete is to be placed shall be shielded from direct sunshine and sprayed with fresh water to prevent excessive absorption of water from the fresh concrete by the surface.
Concrete placing shall be completed as quickly and efficiently as possible, and exposed surfaces shall be immediately covered to reduce excessive evaporation of water from the concrete and conform to the applicable requirement of ACI 301. 

The Contractor shall present for the Owner's approval his proposal for dealing with the following problems related to hot weather concreting:


a) Reduced workability

b) Excessive plastic shrinkage

c) Rapid strength gain but possible low final strength

d) Rapid drying-out of concrete

e) Concrete mixing to counteract hot weather

f) Mixing water to counteract hot weather
Under water concrete shall placed in position by tremie tube specified in Section 17 and contractor shall submit full detailing of the method proposed in advance to the Owner for approval before starting concreting.
CONSOLIDATION OF CONCRETE
Concrete shall be considered by means of mechanical vibrators, subject to the following minimum requirements :


a) Vibrators shall be electric or pneumatic power driven type and shall operate at frequency of 7.000 to 10.500 vibrations per minute for vibrating heads from 80 to 150 mm in diameter and from 8000 to 13500 vibrations per minute for vibrating heads of 30 to 60 mm or greater in diameter when fully immersed.

b) Intensity of vibration shall be such as to visibly affect as a mass of concrete of 250 mm slump over a radius of at least 450 mm.

c) The vibrators shall be inserted and withdrawn out of the concrete slowly. Application of vibrators shall be at points uniformly spaced and not farther apart than twice the radius over which the vibration is visibly effective. If requested by the Owner concrete shall be re-vibrated.

d) Vibration shall not be applied directly on through the reinforcement to sections of layers of concrete which have hardened to the degree that the concrete ceases to be plastic under vibration.

At least one spare vibrator shall be provided for each three vibrators in use for immediate use in the placement.
Vibration shall continue until the concrete has been compacted to its maximum practicable density, and is free from pockets, closes saugly against all surfaces and is in perfect and complete contact with all reinforcement bars and other metal embedded in the concrete. The manufacturer of the vibrators and the total number of vibrators required shall be subject to the approval of the Owner.

Duct banks and slab less than 150 mm thick shall be consolidated by rodding or spading.

Artikel Terkait