1. GENERAL
This
specification defines minimum quality and technical standards governing
materials procurement, application, testing and inspection of offshore pipeline
field joint coatings. This specification
is to be used in conjunction with the following documents:
·
Basis of Design 84506-60-00-2L-060
·
General Specification
84506-60-00-2L-000 - Definitions and Specification Directory
·
General Specification
84506-60-00-2L-010 - Quality Assurance / Quality Control
·
General Specification 84506-60-00-2L-020
- General Offshore Specification
·
DnV OS-F101 Submarine Pipeline Systems
2000
· NACE
RP-02-74 High Voltage
Electrical Inspection of Pipeline Coating Prior to Installation
·
SSPC-SP-1 - Specification for Solvent
Cleaning
·
SSPC-SP-3 - Specification for Power
Tool Cleaning
2. FIELD JOINT COATING REQUIREMENTS
During installation of the pipelines,
the field joint coating station on the laybarge shall be at such level as to
avoid direct wave splash and seaspray.
CONTRACTOR shall use heat-shrink sleeves for anti-corrosion coating and
composite urethane for infill material.
3. PROCEDURES
CONTRACTOR shall submit to COMPANY for approval field joint
coating application procedures.
Procedures shall incorporate actual equipment, materials, surface
preparation, coating application, infill application, repairs and time required
to complete each application using the procedure submitted. COMPANY may request and witness a
demonstration test performed prior to mobilization.
3.1 Application
procedures shall reflect material manufacturer recommendations. Material Technical Datasheets shall be
submitted to COMPANY for each material to assist COMPANY approval of that
material.
4. STEEL PREPARATION
Following COMPANY acceptance of field weld NDT, bare pipe at
the field joints shall be thoroughly cleaned to gray metal per SSPC-SP-3, using
mechanical brushes.
4.1 CONTRACTOR
shall remove any adjacent coating sections not firmly bonded to the pipe. Pipe surfaces shall be free of oil, grease,
moisture, dirt, rust, slivers, burrs, weld spatter, and other material that may
impair proper bonding. Oil and grease
shall be removed using a COMPANY-approved emulsifying detergent or solvent in
accordance with SSPC-SP-1.
4.2 VENDOR-applied
anti-corrosion coating shall be cleaned with a powered brush per SSPC-SP-3 for
at least 50 mm from the exposed steel and feathered to the pipe surface. After cleaning and feathering, CONTRACTOR
shall remove dust from the cleaned surface with a soft brush.
4.3 All prepared surfaces shall be 100% visually
inspected by CONTRACTOR for surface irregularities, such as excessive contours
in the weld bead or weld spatter which would impair the application or
performance of the finished coating. Such defects, if found, will be brought to
the attention of COMPANY and suitable remedial action shall be proposed by
CONTRACTOR for approval by COMPANY.
4.4
Oxidation, tarnishing or contamination
of the cleaned surface is not permitted and all girth weld areas must meet
SSPC-SP-3 standard immediately prior to coating installation. Any girth weld
area that shows signs of oxidation or any girth weld area that remains uncoated
after thirty minutes from preparation shall be re-prepared to the original
specification.
5. HEAT-SHRINK SLEEVE APPLICATION
5.1 CONTRACTOR
shall use Raychem WPC shrink sleeves for infield lines and WPCT-60 shrink
sleeves for export lines or COMPANY-approved equal as anti-corrosion field
joints. Sleeves used shall have
thermochromatic indicators to demonstrate correct and even heating of the sleeve.
5.2 Sleeves
shall be stored in accordance with sleeve manufacturer’s instructions.
5.3 CONTRACTOR
shall apply pre-heat uniformly to the field joint and complete the joint
coating in strict accordance with the manufacturer’s recommendations. Heat-shrink sleeves shall be wrapped around
the field joint, centered on the weld, and shall overlap vendor-applied
anti-corrosion coating by 50 mm and onto itself at
the 12 o’clock position by a minimum of 50 mm after completion of the
joint. A sleeve closure shall be applied
in accordance with manufacturer’s instructions.
6. FIELD JOINT ANTI-CORROSION COATING INSPECTION
6.1 CONTRACTOR
shall fully inspect each field joint anti-corrosion coating prior to joint
infill.
6.2 CONTRACTOR
shall furnish a COMPANY-approved, portable high voltage electronic holiday
detector, with an audible and visual signaling device, and shall test all field
joint coatings immediately after application, for discontinuities, holidays and
pinholes, in strict accordance with NACE RP-02-74. CONTRACTOR shall submit details of the
proposed inspection equipment and inspection procedures prior to start of work,
for COMPANY for approval, including:
·
Type and make of calibrating voltmeter.
·
Grounding techniques for detector and
pipe.
·
Type of search electrode (steel spring,
wet sponge or conductive rubber).
·
Applied output voltage, with a spark
discharge at least twice coating thickness, to assure adequate inspection
voltage and compensate for coating thickness variations.
6.3 The
holiday detector shall be calibrated every twelve (12) hours, or upon
noticeable humidity change, with a CONTRACTOR furnished voltage meter, and by
use on a control joint coating with known holidays.
6.4 CONTRACTOR
shall visibly inspect all field joints for wrinkles, air pockets, adhesive flaw
and correct heating in accordance with sleeve manufacturer’s thermochromatic
indicators. CONTRACTOR shall reject,
remove and replace heat-shrink sleeves if:
·
Air pockets are apparent
·
Wrinkles are visible
·
Overlap with the factory-applied
anti-corrosion coating is less than 50 mm
6.5 The
maximum number of holidays shall not exceed two (2) per field joint coating
area or as recommended by supplier and as detailed in CONTRACTOR’s approved
procedure.
6.6 CONTRACTOR shall submit for approval as
part of the procedures, repair criteria for cuts in the heat shrink sleeve and
repair of holidays.
7. FIELD JOINT INFILL APPLICATION
Following field joint anti-corrosion coating application,
the field joint cavity shall be completely filled with composite urethane to
the same thickness as adjoining concrete coating.
CONTRACTOR shall include as part of the procedures, suitable
methods of storage of infill material. Storage methods will prevent
contamination or deterioration of the material and will be in accordance with
supplier recommendation.
7.1 Composite
Urethane Infill
Composite urethane joint infill shall be Flotec FJ4000 or
COMPANY-approved equal. Following
acceptance of field joint coating, the field joint cavity shall be completely
filled with composite urethane infill to the same level as the concrete
coating.
CONTRACTOR shall propose a suitable mold to fit around the
pipe and contain composite urethane infill material.
Infill material shall be applied in accordance with
manufacturer’s recommendations and to COMPANY satisfaction.
Composite urethane shall have cured sufficiently to ensure
sufficient strength to support the pipe prior to moving the field joint over
any rollers.
8. RECORDS
CONTRACTOR
shall maintain records of all field joint inspection results and relate the
results to each specific field joint number.
Material batch numbers and certificates shall also be related to a
specific field joint number.
On
completion of the WORK, CONTRACTOR shall submit the following information as a
minimum to COMPANY:
·
Heat-shrink sleeve batch certificates
·
Heat-shrink sleeve inspection records
·
Holiday detector calibration
certificates
·
Infill material batch certificates
·
Mold material certificates
·
Application equipment calibration
certificates
·
Infill inspection records
The above data will be supplied in a hard copy format and an
electronic format.